Green Energy Open Access in India – Part 1

geoa part 1

From Monopoly to Market Choice: The Regulatory Journey Towards Green Electricity

By Nomos Finergy LLP

Introduction

The Indian electricity sector is undergoing one of its most significant structural transformations since the enactment of the Electricity Act, 2003. While reforms over the last two decades introduced competition in generation and enabled power trading, the distribution segment largely remained under the control of distribution licensees (DISCOMs). Consequently, most commercial and industrial consumers continued to procure electricity from their local DISCOM, often at tariffs substantially higher than the cost of generation.

The introduction of the Electricity (Promoting Renewable Energy Through Green Energy Open Access) Rules, 2022 (“GEOA Rules, 2022“) represents a decisive policy intervention intended to change this paradigm. Instead of merely promoting renewable energy generation, the Rules seek to democratize access to renewable electricity by enabling eligible consumers to purchase green power directly from generators or through power markets.

This first part of the series examines why Green Energy Open Access became necessary, how the legal framework evolved, and whether the reform has genuinely accelerated India’s transition to a competitive green electricity market.

Frequently Used Nomenclature

Short FormFull Form
EA, 2003Electricity Act, 2003
GEOAGreen Energy Open Access
GEOA RulesElectricity (Promoting Renewable Energy through Green Energy Open Access) Rules, 2022
DISCOMDistribution Licensee
C&ICommercial & Industrial Consumers
SERCState Electricity Regulatory Commission
CERCCentral Electricity Regulatory Commission
APTELAppellate Tribunal for Electricity
RPORenewable Purchase Obligation
RERenewable Energy
CSSCross Subsidy Surcharge
ASAdditional Surcharge
ISTSInter-State Transmission System
GNAGeneral Network Access

(These abbreviations will be used throughout the remaining parts of this series.)

Why was Green Energy Open Access Needed?

Before 2022, open access was legally available under the Electricity Act, 2003. However, in practice, several regulatory and commercial barriers significantly limited its adoption.

Major challenges included:

IssuePractical Impact
Minimum demand of 1 MWExcluded a large number of medium-sized industries.
Different State RegulationsEach State followed different procedures, banking rules and charges.
Delayed approvalsOpen access approvals often took several months.
High Cross Subsidy SurchargeReduced commercial attractiveness.
Additional Surcharge disputesFrequent litigation before State Commissions and APTEL.
Banking restrictionsRenewable generators lost flexibility.

Although the statutory right existed, effective access remained inconsistent across states.

Industry associations such as CII and FICCI repeatedly represented that renewable procurement through open access had become administratively difficult and commercially uncertain, discouraging investment in renewable power procurement.

The Legal Foundation: Electricity Act, 2003

Green Energy Open Access is not a new statutory right. Rather, it is an evolution of the open access framework established under the Electricity Act, 2003.

Section 2(47): Definition of Open Access

“Open Access means the non-discriminatory provision for the use of transmission lines or distribution system or associated facilities…”

Interpretation

This definition establishes that electricity networks are common infrastructure. The owner of the network cannot arbitrarily refuse access if statutory conditions are fulfilled.

Section 42(2)

Section 42 mandates every distribution licensee to introduce open access in phases.

It also permits recovery of:

      • Cross Subsidy Surcharge (CSS)

      • Additional Surcharge (AS), where applicable

    Interpretation

    The legislature attempted to strike a balance between:

        • promoting competition; and

        • protecting the financial viability of DISCOMs.

      This balancing exercise continues to shape almost every open access dispute before Electricity Regulatory Commissions and APTEL.

      Section 39

      Section 39 imposes a similar obligation upon the State Transmission Utility to provide non-discriminatory open access.

      Section 86(1)(e)

      Perhaps the most important provision for renewable energy.

      The State Commission shall:

      “…promote cogeneration and generation of electricity from renewable sources of energy…”

      This single provision became the constitutional basis upon which State Commissions framed renewable energy regulations long before the GEOA Rules were notified.

      The Turning Point: Green Energy Open Access Rules, 2022

      The Ministry of Power notified the Electricity (Promoting Renewable Energy through Green Energy Open Access) Rules, 2022 on 6 June 2022, exercising powers under Sections 176 and 183 of the Electricity Act, 2003. The objective was to remove barriers that had hindered renewable energy procurement through open access.

      The Rules introduced several structural reforms:

      Earlier PositionGEOA Rules, 2022
      Minimum demand: 1 MWReduced to 100 kW
      State-wise application processNational single-window portal
      Approval delaysDeemed approval after 15 days, subject to prescribed conditions
      Limited banking clarityBanking framework recognised
      High uncertainty in chargesPrinciples for transmission, wheeling, CSS, standby and banking charges specified

      The reduction of the eligibility threshold from 1 MW to 100 kW significantly expanded the potential market by allowing medium-sized commercial establishments, hospitals, educational institutions and manufacturing units to procure renewable electricity directly.

      Did the Reform Work?

      This is perhaps the most important question.

      The answer appears to be yes—but with qualifications.

      According to the Institute for Energy Economics and Financial Analysis (IEEFA):

      IndicatorObservation
      Annual C&I Open Access RE CapacityGrew by 90.4% between FY2023 and FY2024
      State adoptionAlmost all States have initiated alignment with GEOA Rules
      Remaining challengeImplementation remains uneven across States

      IEEFA nevertheless observes that coordination issues between State nodal agencies and DISCOMs, along with differing interpretations of banking and charges, continue to create practical bottlenecks.

      Is India Actually Transitioning to a Competitive Green Market?

      The answer requires nuance.

      Positive developments

      ✔ Lower eligibility threshold

      ✔ Faster approvals

      ✔ National portal

      ✔ Growing corporate ESG commitments

      ✔ Competitive renewable tariffs

      ✔ Rapid increase in C&I renewable procurement

      Persistent structural issues

      ✖ Banking restrictions differ across States

      ✖ High CSS in several jurisdictions

      ✖ Additional Surcharge disputes

      ✖ Delays in operational approvals

      ✖ Frequent regulatory litigation

      Consequently, India has successfully created the legal architecture for Green Open Access, but the efficiency of the transition still depends heavily on State-level implementation.

      Emerging Role of APTEL

      Almost every major regulatory reform in the electricity sector ultimately reaches APTEL.

      Although many disputes pre-date the GEOA Rules, APTEL has consistently emphasized certain guiding principles in open access jurisprudence:

          • Open access is a statutory right under the Electricity Act, 2003 and cannot be defeated through administrative action.

          • Charges imposed on open access consumers must have a statutory and regulatory basis.

          • Regulatory Commissions must balance renewable energy promotion with the financial sustainability of distribution licensees.

          • Open access restrictions cannot be arbitrary or discriminatory.

        In subsequent parts of this series, we will examine landmark APTEL decisions—including disputes relating to additional surcharge, cross-subsidy surcharge, banking, captive status and renewable procurement—and analyse how these rulings have shaped the implementation of Green Energy Open Access.

        Author’s Perspective

        Green Energy Open Access is often presented as a renewable energy policy. That description is only partially accurate.

        In reality, GEOA represents a market-design reform.

        Its success should therefore not be measured solely by the number of megawatts of renewable energy added, but by whether consumers can genuinely exercise choice without facing unnecessary procedural barriers or unpredictable regulatory costs.

        The coming years will determine whether India completes this transition from a DISCOM-centric electricity supply model to a consumer-centric competitive electricity market.

        References 

        Primary  Sources

          1. Ministry of Power – Electricity (Promoting Renewable Energy Through Green Energy Open Access) Rules, 2022 and Amendments

          2. Press Information Bureau – Green Energy Open Access Rules, 2022 Overview

          1.  

          Regulatory & Research References

            1. IEEFA Report: Impact of Green Energy Open Access Rules, 2022
            2. Green Open Access Registry – State Regulations Repository
            3. APTEL Judgments Database
            1.  

            1.  

            1.  

            Disclaimer

            This article is intended solely for educational and informational purposes. It does not constitute legal, regulatory, financial or commercial advice. Although every effort has been made to rely upon authentic statutory provisions, government notifications, regulatory documents and judicial decisions available at the time of writing, readers should verify the latest amendments, regulations and judicial pronouncements before acting upon any information contained herein. The interpretations expressed are those of the author and are intended to encourage informed discussion on India’s evolving electricity market framework.

            Leave a Comment

            Your email address will not be published. Required fields are marked *

            Scroll to Top